Fulton Street road restoration will bring lane closures
|
Starting September 24th, a new reinforced-concrete roadway will be installed outside 96 Fulton Street, between William and Gold. The operation will continue for approximately three weeks, through mid-October 2012, and will require temporary suspension of parking on that block. Pedestrian walkways will be maintained. City Department of Design and Construction crews will excavate the old roadway, install rebar, and install new concrete. Regular 7 a.m. to 3:30 p.m. work hours will be in effect, with some weekend work needed. The new roadway is part of the city's Fulton Street Corridor Phase 2 project.
|