 |
| |
| |
Franklin Street Closed Tonight
|
| |
The new 18-story residential tower at 50 Franklin Street topped out last month, with contractor CM & Associates now performing façade and utility work. Tonight, crews will use a crane to install the building’s cooling tower on its roof. The operation requires the full closure of Franklin Street between Lafayette and Broadway starting at 8 p.m. Pedestrian access will be maintained. The building is slated to open in March 2009.
|
|
| |
Nassau Street Utility Work and Lane/Road Closures
|
| |
On Monday, June 23rd, Con Edison began utility work on the east side of Nassau Street between Beekman and Spruce Streets. The work is expected to continue for approximately four weeks. On weekdays from 7 a.m. to 3:30 p.m., one lane of traffic will be maintained; on weekends from 8 a.m. to 4:30 p.m. a full road closure will be in effect.
|
|
| |
Intersection Closed on Beekman and Nassau
|
| |
The New York City Department of Design and Construction (DDC) with Con Edison will perform intermittent off-hour reconstruction work which will require the overnight closure of Beekman Street intersections at Nassau Street and William Street for the next three months. The closure is scheduled for June 2 through August 29 and will be in effect from 7:00 PM to 7:00 AM.
|
|
| |
Temporary Reversal of New Street Starts June 16
|
| |
As part of the work at 40 Broad Street, New Street will be temporarily reversed between Beaver and Broad Streets beginning Monday, June 16th. The reversal makes that block of New Street northbound for approximately four weeks. Located entirely within the New York Stock Exchange security zone, the traffic change allows crews to alter construction-ramp access on the west side of the building.
|
|
| |
Lane Changes on Broadway at Fulton Street
|
| |
On Monday, March 31st, 2008, Fulton Street Corridor utility work on Broadway between Vesey and Fulton Streets will shift to the two west lanes. Those lanes will be closed to vehicles for approximately two months, while the two east lanes will remain open at all times.
|
|
| |
Month-Long Closure on Hudson at Chambers Street
|
| |
Hudson Street is currently closed between Chambers and Reade Streets for Metropolitan Transportation Authority crews to begin elevator installation at the 1/2/3 Chambers Street subway station.
|
|
| |
Fulton Street Road and Lane Closures
|
| |
The city Department of Transportation has revised the traffic pattern to accommodate the capital reconstruction of Fulton Street, which began in July 2007. The project will replace Fulton Street’s 150-year-old water main, as well as upgrade utilities and improve the street’s drainage system.
Fulton Street between Broadway and Nassau is closed to vehicles as of September 2007. Work is being coordinated with the MTA, which is at work on the adjacent Fulton Street Transit Center.
|
|
| |
Dey Street Closure
|
| |
As part of the MTA’s Fulton Street Transit Center (FSTC) project, Dey Street was closed to through traffic on October 3, 2005. Coordinated street access will be available for deliveries and emergency vehicles, and pedestrian access will be maintained.
|
|
|
|
| |
|
|
|
|
 |
| |
| |
Express Bus Stops Relocated on Church Street |
| |
To accommodate the deconstruction of 99 Church Street, located between Barclay Street and Park Place, New York City Transit has relocated stops for five express bus stops.
The BXM4 and BXM18 stops have been relocated one block north to Church Street between Park Place and Murray Street. The QM1A, QM11, and QM24 have been relocated around the corner to Park Place between Broadway and Church Street.
|
|
|
|
|
|
 |
| |
| |
Air Monitoring Results Following Fire at 130 Liberty Street |
| |
The Department of Environmental Protection (DEP) continues to oversee air quality testing at the 130 Liberty Street site. Air monitoring is ongoing. To date, 183 samples have been taken from 22 locations.
Crews are continuing their work to reseal floors that were compromised during the August 18th fire. At the same time, work is also continuing to improve fire safety. The work to seal the building will continue up to the 19th floor. The floors above the 19th have already been abated.
|
|
|
|
|
|
|
|
|
|
|
|
| |
LMCCC Air Monitoring Program |
| |
The Lower Manhattan Construction Command Center (LMCCC) has implemented an air quality monitoring program to monitor the cumulative impact of all Lower Manhattan construction projects. The LMCCC is conducting daily air monitoring at the following sites throughout Lower Manhattan: 292 Greenwich Street, 80 Catherine Street, 1 World Financial Center and 154 Nassau Street.
|
|
|
|
|
|
 |
| |
| |
Block-Long Sidewalk Closure on Church Street at WTC |
| |
To help facilitate the massive excavation of the World Trade Center (WTC) east bathtub, the Port Authority closed the western sidewalk of Church Street between Liberty and Cortlandt Streets in July 2007.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
| |
| |
The NYC program will send messages to participants about significant events impacting the Lower Manhattan area. A significant event is any emergency with potential to compromise public health or safety.
To register to receive emergency alerts pertaining to Lower Manhattan through the Noticy NYC program, please click here. |
|
|
|