*Last updated March 5, 2010
WEDNESDAY March 3, 2010
DAY: Work Shift Is From 7:00 am to 7:00 pm
Operation #1 No work
Location: Liberty St. From: Nassau St. – William St.
Operation #2 No work
Location: Pearl St. From: John St. – Fulton St.
Operation #3 Continue back filling
Location: Louise Nevelson Plaza From: Liberty St. from William St. –Gold St.
Operation #4 No work
Location: Maiden Lane From: Gold St. - William St.
Operation #5 Water shut down for 10 Liberty to lower utilities
Location: Liberty Street From: Gold St. - William St
Operation #6 No work
Location: Maiden Lane Intersection From: Water St.- Pearl St.
THURSDAY MARCH 4, 2010
DAY: Work Shift Is From 7:00 am to 7:00 pm
Operation #1 No work
Location: Liberty St. From: Nassau St. – William St.
Operation #2 No work
Location: Pearl St. From: John St. – Fulton St.
Operation #3 Continue back filling
Location: Louise Nevelson Plaza From: Liberty St. from William St. –Gold St.
Operation #4 No work
Location: Maiden Lane From: Gold St. - William St.
Operation #5 Water shut down for 10 Liberty to lower utilities
Location: Liberty Street From: Gold St. - William St
Operation #6 No work
Location: Maiden Lane Intersection From: Water St.- Pearl St.
FRIDAY MARCH 5, 2010
DAY: Work Shift Is From 7:00 am to 7:00 pm
Operation #1 No work
Location: Liberty St. From: Nassau St. – William St.
Operation #2 No work
Location: Pearl St. From: John St. – Fulton St.
Operation #3 Continue back filling
Location: Louise Nevelson Plaza From: Liberty St. from William St. –Gold St.
Operation #4 No work
Location: Maiden Lane From: Gold St. - William St.
Operation #5 Water shut down for 10 Liberty to lower utilities
Location: Liberty Street From: Gold St. - William St
Operation #6 No work
Location: Maiden Lane Intersection From: Water St.- Pearl St.
------------------------------------------------------------------------------------------------------
THE DDC CONTINUES WORK ON LIBERTY STREET
The New York City Department of Design and Construction (NYCDDC) is managing a capital construction project along Liberty Street between Nassau and Gold Streets, Maiden Lane between William and Water Streets and Pearl Street between Fulton and John Streets. In addition, the Louise Nevelson Plaza will be reconstructed.
WORK COMPLETED AS OF DECEMBER, 2009
Below is a list of work locations and activities that have been completed to date:
Location 4: Maiden Lane (Water Street – Gold Street):
- Completed new sidewalk and new pedestrian ramp at the intersection of Maiden Lane and Pearl St.
- Completed new curb and road base at Maiden lane and Gold St.
- Maiden Lane Detour has been eliminated
WORK SCHEDULED: JANUARY - FEBRUARY 2010:
Below is a list of work locations and activities slated to occur / to be completed:
Location 1: Liberty Street (Nassau Street–William Street):
- Complete catch basin installation and complete roadway from William St to Gold St.
Location 2: Pearl Street (Fulton Street- John Street):
Location 3: Louise Nevelson Plaza:
- Complete drilling and grouting operation.
- Back fill plaza begin reconstruction of park
Location 4: Maiden Lane (Water Street – Gold Street):
- Complete Con Edison Vault modification and roadway reconstruction
Location 5: Maiden Lane (Gold Street- William Street):
- Roadway reconstruction
- Utility relocation
- Trenching work at the intersection of Maiden Lane and William Street
|