| Project Updates |
|
| Fulton Street Transit Center |
« back |
|
Summary | Daily Activities | Contact Info | FAQs | Links
|
|
| Fulton Street Station foundation work, October 2008 |
Work on the transit hub at Fulton Street began in early February 2005 -- the first steps on the way to a station that links 12 subway lines and will accommodate more than 300,000 riders daily.
The MTA announced in January 2008 that the transit center's main building likely will not be built as planned due to escalating construction costs. However, other project elements -- including the Dey Street Concourse and headhouse, Corbin Building restoration and new entrances, and other station "rationalization" features within the station -- are proceeding.
A revised plan for the main building, on the southeast corner of Broadway and Fulton, is expected in the second half of 2008.
The project is expected to be complete in 2010.
Click here to learn more about project in depth.
Locate this project on the Interactive Streetwork Map.
|
Summary
|
|
NOTICE: The Broadway-Nassau station entrance on the south side of Fulton Street east of Broadway closed in April 2008. Alternately, riders can use the entrance on the north side of Fulton Street.
|
|
|
Daily Activities
|
|
*The following information was last updated on September 26, 2008.
Dey Street Pedestrian Concourse
- Starting mid-August 2008: Sidewalk closure (with pedestrian sheep run in the curb lane) on Broadway at Dey for 4/5 subway box roof repair through mid-October 2008
- As of August 20, 2005: The Cortlandt Street R/W station is closed. Work included underpinning the subway track and platform structure, and widening the station platforms and roof. Coordination is taking place with the Port Authority for its East Bathtub construction project. The northbound platform may reopen in late 2008; the southbound platform reopening will likely coincide with the 2012 completion of WTC Towers 2, 3 and 4.
- As of October 3, 2005: Dey Street is closed to vehicular traffic through November 2008. Partial access is available for deliveries and emergency vehicles, and pedestrian access is maintained. The closure allows crews to build the underground pedestrian concourse under Dey Street that will link the FSTC with the World Trade Center Transportation Hub.
- Crews are working on the east side of Church Street from Dey to Fulton Streets as part of the utility and structural work for the concourse, including new station entrances.
- Crews are constructing the new Dey Street headhouse at the southwest corner of Broadway and Dey, and are currently forming its concrete structure. Finishing contract to be awarded in fall 2008.
Main Building Site (Broadway at Fulton)
- Secant-wall installation and foundation work inside the work site on Fulton near Broadway began in late July and continues through November 2008
- The contract for foundation work and underpinning of the Corbin Building will be awarded in September, with work planned to begin in fall 2008
- Two traffic lanes and a pedestrian walkway will be maintained on Broadway.
|
|
|
Contact Info
|
|
For more information about this project, call the MTA's Fulton Street Tranist Center hotline at 646 252 2670, or visit their website at www.mta.info to submit questions via e-mail.
MTA construction alerts can be found here.
|
|
|
Frequently Asked Questions
|
|
Q:
|
When will this project be completed?
|
|
A:
|
Though some sections of the Fulton Street Transit Center are being completed earlier, the entire complex is expected to be complete by fall 2010.
|
|
Q:
|
Why is the MTA building a new Fulton Street subway station?
|
|
A:
|
The current Fulton Street-Broadway-Nassau subway station is a collection of subway lines that were built by three independent transit companies in the early 20th century. The result of connecting those lines -- the 2/3, 4/5, A/C, and J/M/Z -- was a tangle of corridors and stairways that even seasoned riders can get lost in.
|
|
Q:
|
Why will the Fulton Street Transit Center take so long to build?
|
|
A:
|
As the new transit center is built, the MTA plans to keep trains in operation and is making every effort to minimize disruption for the neighborhood’s homes and businesses. Those factors have a significant impact on scheduling, which is broken down into six phases that each last one to two years.
|
|
Q:
|
How will construction on the Fulton Street Transit Center affect my commute?
|
|
A:
|
Because much of the new transit center work will take place while subways are operating, commuters should expect occasional delays in service. The MTA will work on the new center seven days a week, but it plans to limit train diversions to nights and weekends as much as possible. Visit the Alerts section of LowerManhattan.info or www.mta.info, or call 311 for the very latest on subway diversions.
|
|
Q:
|
Will their be air monitoring or noise pollution guidlines on the site?
|
|
A:
|
LMCC/LMDC monitors air quality via a network of community air monitors in Lower Manhattan. The MTA CC will perform work area monitoring for asbestos, mold and metals throughout the remediation phase at 189 Broadway, scheduled to begin mid-November. Asbestos surveys and site evaluations are currently underway at the buildings east of Broadway and the remediation and deconstruction of these buildings will occur within the first quarter of 2007. MTA CC adheres to the Environmental Performance Commitments developed to minimize the cumulative effects of the Lower Manhattan Recovery projects. In addition, MTA CC contractors must keep construction noise levels within 5 dBA (1-hour Leq) of ambient noise at residential buildings.
|
| |
|
Click here for answers to commonly asked construction questions. |
|
|
|
|
 |
 |
 |
 |
You must have Flash player 7 to view this content. Download flash now.
|
|