Project Updates Printer Friendly Version
Beekman Street/Park Place Reconstruction « back
Summary | Daily Activities | Contact Info | FAQs | Links

This work is part of the Beekman and Park Place Reconstruction Project 
Beekman Street and Park Place reconstruction began in 2007
As part of its plan to improve and update downtown’s infrastructure, the city Department of Design and Construction (DDC) launched the capital reconstruction of Beekman Street and Park Place in late October 2007.

The city posts signs for traffic changes and road/lane closures as they occur. Together with the Lower Manhattan Construction Command Center, the DDC also hosts periodic community stakeholder meetings.

Click here for a tour of the rebuilding projects taking place in Lower Manhattan.

Locate this project on the Interactive Streetwork Map.


Summary

BEEKMAN STREET: Capital reconstruction continues on Beekman Street from the firehouse (midblock) to Gold Street through November 2009. Crews have closed that half-block of Beekman, and will work weekdays from 7 a.m. to 7 p.m. and weekends as necessary.

Work also continues on Beekman from Park Row to Nassau Street, with a full road closure in effect through April 2010 (in two segments - Nassau to Theater Alley, and Theater Alley to Park Row).

PARK PLACE: Reconstruction work is underway on the north side of Park Place between Church Street and Broadway. Westbound traffic will be prohibited, but two eastbound traffic lanes will be maintained throughout project. Buses on that block of Park Place are re-routed to Warren Street on October 13th. Work there continues through appx. November 2009.

Con Edison electric work will occupy the east lane of Church between Park Place and Barclay Street from mid-October through mid-November 2009.


Daily Activities

*The following information was last updated November 20, 2009

FRIDAY- NOVEMBER 20, 2009

DAY: Work Shift Is From 7:00 am to 3:30 pm

Operation #1  PARK PLACE
                          Contractor working on new sewer.
NIGHT: Work Shift is from 11:00 pm to 7:00 am                                          
                         
 No work scheduled

Operation #2  BEEKMAN STREET (GOLD ST. TO 48 BEEKMAN ST).
DAY: Work Shift is from 7:00 am to 3:30 pm                                           
                        
 Contractor doing curb installation and concrete pour for bus pad.
DAY: Work Shift Is From 7:00 am to 3:30 pm

Operation #3  BEEKMAN STREET (THEATRE ALLEY TO NASSAU STREET)
                         Work completed but cannot begin next phase until Beekman Towers deliveries are completed
NIGHT: Work Shift is from 11:00 pm to 7:00 am
                        
No work scheduled


SATURDAY- NOVEMBER 21, 2009

DAY: Work Shift Is From 8:00 am to 3:30 pm

Operation #1  PARK PLACE
                       
  No work scheduled
NIGHT: Work Shift is from 11:00 pm to 7:00 am                                          
                        
 No work scheduled

Operation #2  BEEKMAN STREET (GOLD ST. TO 48 BEEKMAN ST).
DAY: Work Shift is from 7:00 am to 3:30 pm                                          
                        
 Con Edison working on intersection
DAY: Work Shift Is From 8:00 am to 3:30 pm

Operation #3  BEEKMAN STREET (THEATRE ALLEY TO NASSAU STREET)
                        
 No work scheduled.
NIGHT: Work Shift is from 11:00 pm to 7:00 am
                        
No work scheduled


SUNDAY- NOVEMBER 22, 2009
                        
No work scheduled


MONDAY- NOVEMBER 23 2009

DAY: Work Shift Is From 7:00 am to 3:30 pm

Operation #1  PARK PLACE
                         
 Sewer work on schedule.
NIGHT: Work Shift is from 11:00 pm to 7:00 am                                           
                         
 No work scheduled

Operation #2  BEEKMAN STREET (GOLD ST. TO 48 BEEKMAN ST).
DAY: Work Shift is from 7:00 am to 3:30 pm                                          
                        
 Con Edison and contractor working on site
DAY: Work Shift Is From 7:00 am to 3:30 pm

Operation #3  BEEKMAN STREET (THEATRE ALLEY TO NASSAU STREET)
                         
Work completed but cannot begin next phase until Beekman Towers deliveries are completed
NIGHT: Work Shift is from 11:00 pm to 7:00 am
                        
No work scheduled

TUESDAY- NOVEMBER 24 2009

DAY: Work Shift Is From 7:00 am to 3:30 pm

Operation #1  PARK PLACE
                        
 Sewer work on schedule.
NIGHT: Work Shift is from 11:00 pm to 7:00 am                                          
                        
 No work scheduled

Operation #2  BEEKMAN STREET (GOLD ST. TO 48 BEEKMAN ST).
DAY: Work Shift is from 7:00 am to 3:30 pm                                          
                        
 Con Edison and contractor working on site
DAY: Work Shift Is From 7:00 am to 3:30 pm

Operation #3  BEEKMAN STREET (THEATRE ALLEY TO NASSAU STREET)
                         Work completed but cannot begin next phase until Beekman Towers deliveries are completed
NIGHT: Work Shift is from 11:00 pm to 7:00 am
                         
No work scheduled

WEDNESDAY- NOVEMBER 25 2009

DAY: Work Shift Is From 7:00 am to 3:30 pm

Operation #1  PARK PLACE
                        
Sewer work on schedule.
NIGHT: Work Shift is from 11:00 pm to 7:00 am                                          
                        
 No work scheduled

Operation #2  BEEKMAN STREET (GOLD ST. TO 48 BEEKMAN ST).
DAY: Work Shift is from 7:00 am to 3:30 pm                                          
                        
 Con Edison and contractor working on site
DAY: Work Shift Is From 7:00 am to 3:30 pm

Operation #3  BEEKMAN STREET (THEATRE ALLEY TO NASSAU STREET)
                        
 Work completed but cannot begin next phase until Beekman Towers deliveries are completed
NIGHT: Work Shift is from 11:00 pm to 7:00 am
                        
No work scheduled


NO WORK SCHEDULED FOR NOVEMBER 26, 27, 28,29th

HAPPY THANKSGIVING!

------------------------------------------------------------------------------------------------------

TRAFFIC PATTERN/STREET PARKING CHANGES:

STARTING SATURDAY AUGUST 15, 2009, AND CONTINUING UNTIL NOVEMBER 2009.

On Saturday August 15, 2009, and every Saturday and Sunday until completion, the New York City Department of Design and Construction (DDC) will begin reconstruction of the intersections at Nassau Street and at Theatre Alley at Beekman Street. This work will include city sewers and utility reconstruction as well as the construction of new curbs, sidewalks, and roadways. 

TRAFFIC IMPACTS:  (Park Row – Nassau Street)

  • No traffic will be allowed onto Beekman Street from Park Row.
  • No traffic will be allowed onto Beekman Street from Theater Alley.
  • No traffic will be allowed to enter Nassau Street from Ann Street.
  • Only Emergency Vehicles, vehicles making deliveries, and vehicles going to the Public Parking Garage on Beekman Street, will be allowed to enter the area on William Street.

COMMUNITY IMPACTS:

  • Hours of Operation: work will be performed on weekends (mainly Saturdays) 8:00am to 8:00pm.
  • Noise: The Beekman/Park Place Project is being monitored and is in conformance with New York City Noise regulations. 

Traffic lmpacts: Vehicular traffic will be affected by this work. Parking will be temporarily restricted. Signs will be posted. We appreciate your cooperation and thank you for your patience while we rebuild New York City's infrastructure.

------------------------------------------------------------------------------------------------------

THE BEEKMAN STREET & PARK PLACE PROJECT

The New York City Department of Design and Construction (DDC) continue work on the Beekman/Park Place infrastructure project. This Joint Bid Project offers the opportunity to maintain and/or upgrade community services such as electric, gas, steam, water, sewer at the same time causing less disruption to the community. DDC appreciates your patience and cooperation while we diligently rebuild our city’s aging infrastructure.

BEEKMAN STREET STATUS:

Work completed:

  • Curb on the north and south side has been installed between Nassau Street and Theatre Alley Intersection. The work by Con Edison at Theatre Alley has been completed.

Current work:

  • Utility work on Beekman between 49 Beekman Street and Gold Street is continuing on schedule. Con Edison has completed building a new manhole at the intersection of Gold Street.
  • Con Edison will be working some Saturday’s during months of November and December at Beekman/Gold intersection. The intersection at Nassau Street has been backfilled and temporally asphalted, so that trucks can enter through Park Row for deliveries to Beekman Towers. 

Upcoming work: November - December, 2009

  • Beekman Street (49 Beekman – 7 Gold Street) Con Edison will complete work sometime in December and depending on the weather conditions, the remaining curb and sidewalk will be completed.

PARK PLACE STATUS:

Work completed:

Approximately one third of the curb has been installed on the north side.

Current work:

Excavation will continue on site, this will be followed by installation of new utilities.

Upcoming work:  November and December, 2009

Con Edison and contractor will complete all utility work including sewer replacement. Final paving will be done weather permitting.

**FYI: The Lower Manhattan Development Corporation (LMDC) offers the Small Firm Assistance Program for businesses affected by construction. For more information call: 212-587-9741 or go to:

www.renewnyc.com/ProjectsAndPrograms/

------------------------------------------------------------------------------------------------------

 
Note: Due to unforeseen conditions it may become necessary to change some scheduled work locations and operations. For further information please call Maurice Mayer at (212) 608-4730. To subscribe or unsubscribe to the daily construction bulletins, please visit our website or just click on www.outreachny.com, click on the mail list button, and then follow instructions. Thank you.   


Contact Info

For more information on the Beekman Street/Park Place Reconstruction Project, please call community liaison Maurice Mayer at (212) 608-4730. Stakeholders can submit questions or subscribe to email updates at BeekmanParkPlaceCCL@gmail.com.


Frequently Asked Questions

Q: What is this project's work timeline?
Q: What utility work will happen?
Q: How will it affect the community and businesses?
Q: What transit changes will occur?
 
Click here for answers to commonly asked construction questions.

Related Links

Beekman Street/Park Place Community Outreach Brochure
Get It Fast: Latest Advisories
Looking Ahead rebuilding projects
Special Feature
> Construction Lingo
> Construction Questions Answered
> Support the Memorial
> Envisioning the Future
Headline
- Three Questions for Rich Dalessio, Fiterman Hall
- Cortlandt St Northbound Subway Platform Reopens
- Washington and Carlisle to Close for Crane Removal
- BPC Site 23 Crane Removal to Close Warren Street
- Rector Street Utility Work Extended
- WTC Memorial Plaza on Schedule for 2011 Opening
Community Happenings

Current Construction | Programs in Lower Manhattan | Get It Fast Latest Advisories | News and Image Gallery | About the LMCCC
Home | Search | Fraud Prevention | Get Email Updates | Media Center | Information Library | Contact Us | Navigating This Site

© 2009 Lower Manhattan Construction Command Center/LMDC

RSS Feed - Really Simple Syndication RSS Feed